Construction Nayagaon to Hanotiya road, Length 4.20 Km. 1st Call, PAC Rs. 357.12 Lacs on Road and Bridge Works SOR 11.04.2025 (Ammend-ment upto date), Completion period 180 days i/c rainy season.
Pwd- Roads and Bridges · Madhya Pradesh
Awarded contract value
₹3.00 Cr
Won by RAJLAXAMI DEVBUILD INDIA PRIVATE LIMITED · 4 contracts on record
- Department
- PWD- Roads and Bridges
- State
- Madhya Pradesh
- Contract date
- 21 Aug 2026
- Winning bids
- 1
More from PWD- Roads and Bridges
444 in totalThe same buyer goes to market repeatedly — these are its other awarded contracts.
- Ordinary repairing work of Govt. residential building under P.W.D. Sub Division Alirajpur Division Alirajpur.Madhya Pradesh₹11,02,365
- Maintenance and varius repairng work WPC shutters Viterified flour and wall tiles etc work in Non Justice bunglow in MPHC under HQ section in Hq no 3 jbpMadhya Pradesh · 23 Oct 2026₹16,91,459
- Repairing of Bridge culvert shoulder repair and other repair works in Kantangi section under HQ sub Dn no 1 jbpMadhya Pradesh · 23 Oct 2026₹9,99,200
- Repairing of Bridge culvert shoulder repair and other repair works in Panagar section under HQ sub Dn no 1 jbpMadhya Pradesh · 23 Oct 2026₹9,99,200
- Repairing of Bridge culvert shoulder repair and other repair works in Majholi section under HQ sub Dn no 1 jbpMadhya Pradesh · 23 Oct 2026₹9,99,200
- Construction of Dhamnar to Chhajukheda via Babrecha Daloda, Ladusa, Luhari, Chhayan, Rasulpura road length 22.03 km including pole shifting Division MandsourMadhya Pradesh · 22 Oct 2026₹18.62 Cr
Also won by RAJLAXAMI DEVBUILD INDIA PRIVATE LIMITED
Other contracts this firm has won — who you would be bidding against.
- Construction of Bankhedi Umardha Mathni Sandiya road, Length 3.10 Km. under P.W.D. Sub Division, Pipariya. 1st Call, PAC Rs. 286.78 Lacs on Road Bridge Works SOR 11.04.2025 (Ammendment upto date), Completion period 120 days i/c rainy season.Madhya Pradesh · 22 Sept 2026₹2.58 Cr
- Construction of Bachawani to Andhian Babri road. 1st Call, PAC Rs. 260.88 Lacs on Road Bridge SOR 11.04.2025 (Ammendment upto date), Completion period 150 days i/c rainy season.Madhya Pradesh · 14 Jul 2026₹2.41 Cr
- Construction of Bhairopur to Chandon road, Length 1.50 Km. 1st Call, PAC Rs. 203.03 Lacs on Road Bridge SOR 11.04.2025 (Ammendment upto date), Completion period 150 days i/c rainy season.Madhya Pradesh · 14 Jul 2026₹1.89 Cr
Source
Captured from the official Award of Contract record on the government e-procurement portal (Madhya Pradesh). Tender reference 2026_PWDRB_501176_1.
Open the government portal ↗This is a completed (awarded) contract shown for market reference — what the government actually paid for this work. Always verify on the official portal. Bidrove is an independent platform, not affiliated with any government authority.